Description

Probam is commissioned by Carrefour to follow up every aspect of the project and to ensure a team spirit is generated between the various parties involved – architect, client, technical offices and various contractors – so that they will be able to make the deadline.

The works include adaptations of the building structure, a complete technical installation (electricity, data, security, sprinkler system, hvac, sanitary fittings) in the shop, flooring, paintwork, ordering all new refrigerators, shelves and other shop furniture and materials.

Figures

  • an average floor surface of 8000 m²
  • time needed for remodelling: approx. 3 months

Project details

  • ClientCarrefour
  • Statusdelivered
  • LocationDrogenbos
  • Project start2011
  • Project end2011
  • ArchitectMercomet NV Ukkel
  • Engineering company technical installationsEDT (electricity) and Navitas (hvac)